Client

JTC Corporation

Construction Period

17 May 2018 – May 2022

Scope of Works

Sand Supply
Drainage Works
Rock Works

Sand Supply & Reclamation

6,800,000 m³

Drainage Works

3,787 m

Rock Works

44,300 m³

Construction Period

Feb 2013 – May 2015 (27 months)

Contract Amount

S$ 223 million

Civil and Reclamation Works, Jurong Island, Singapore

Project Overview: YTC Construction, in partnership with Hyundai, embarked on an exceptional journey of civil and reclamation works at Jurong Island, Singapore. This project underscores our unwavering commitment to excellence in engineering and construction.

Key Project Details:

  • Location: Jurong Island, Singapore
  • Main Contractor: Hyundai – YTC Joint Venture
  • Sand Supply & Reclamation: A substantial effort, involving 6,800,000 cubic meters of sand, to shape and expand the coastline.
  • Drainage Works: Spanning 3,787 meters, drainage works were meticulously executed to manage water resources effectively.
  • Rock Works: 44,300 cubic meters of rock were strategically placed to fortify the site against coastal forces.
  • Construction Period: From February 2013 to May 2015, a dedicated timeline of 27 months was devoted to this transformative endeavor.
  • Contract Amount: A total of S$ 223 million was invested in this visionary project.

At YTC Construction, we don’t just build structures; we create legacies. This project exemplifies our expertise in civil and reclamation works, shaping environments that stand the test of time and contribute to the advancement of Singapore’s infrastructure.